STAGE 1. DELIVERY AND INSTALLATION
UOG-15 plant arrives at the working site in containers carried in a truck with a trailer or semi-trailer as well as in a separate truck with tanks, sleeves and 9 to 12 meters attachments, depending on the scope of delivery.
Unloading of equipment is carried out by a team using a crane or manipulator with lifting capacity of 12 tons. All major components are prepared for top slinging.
At the same time the extra equipment comes on site - diesel generator set (DGS), the mobile steam generator, a bucket loader and dump trucks.